PM-KUSUM
Where on a farm feeder can solar connect?
- PM-KUSUM Component A: plants of 500 kW to 2 MW within 5 km of the substation. Component C: feeder solarisation sized from 3 years of feeder farm energy at 19% CUF (10 lakh units a year needs about 600 kW). checked-correct (MNRE guideline, expert review; not re-read here)
- Telangana: Component A was cut from 4,000 MW to 1,000 MW on 31 Jan 2025 and the state is pursuing restoration; Component B none; Component C 28,000 pump sets. checked-correct (TGERC order 32/2025, expert review; not re-read here)
- Farm supply is 9 daytime hours in Andhra Pradesh; the Telangana pattern is not confirmed. Solar peaks with pump load, which limits reverse flow only if the pumps run. AP pattern as stated by expert review; Telangana: cannot be checked yet, because the schedule is not confirmed
- Pump-transformer ratings and midday pump load: nothing on file. cannot be checked: input needed from the discom
Pump transformers in this grid: The 25 kVA pump transformer and 15 kW per pump at pf 0.8 are a scenario, input needed from the discom: not a measured or discom value.
- Pump-transformer ratings (kVA) and consumers per pump transformer: input needed from the discom.
- Midday pump load by feeder (15-minute feeder metered load) and the real pump supply schedule in Telangana: input needed from the discom.
| Cap reading | Cap MW (unit assumed) | Engineering max MWp | Engineering / cap | Cap is |
|---|---|---|---|---|
| 50% of feeder max load (0.45 MW pumps) | 0.225 | 4.75 | 21.1 | tighter than engineering |
| 50% of substation 5 MVA | 2.500 | 4.75 | 1.9 | tighter than engineering |
- Assumed rural 11 kV agricultural feeder, 15 km, 30 pump transformers; no real feeder is held.
- Pump transformers: assumed 25 kVA, 15 kW per pump at pf 0.8 when running: a scenario, input needed from the discom.
- Pumps running means daytime pump load is on the feeder, which raises the room.
- The 1.03 pu setting is applied through a 1.25% tap step, so the actual no-load sending-end voltage is 1.025 pu (stored 1.0249); the 1.00 setting gives 0.9999 pu.
- Checked limits: 11 kV voltage up to +6%, line loading 100% and substation transformer loading 100%. The pump transformers (assumed 25 kVA) and their low-voltage side are not checked.
Precomputed grid: every value was calculated offline on an assumed feeder and stored. The slider picks a stored row; it does not run a power flow.
These values are MODEL EXAMPLE precomputed on an assumed feeder (see assumptions), not recalculated live. Outputs are screening, example values, never approved capacity.
Estimate on an assumed feeder, read from the precomputed grid. Above 2 MWp: what the feeder could carry, not a plant size. PM-KUSUM Component A plants are 500 kW to 2 MW within 5 km of the substation [checked-correct, MNRE guideline; not re-read here].
- Pump transformers and farm load: nothing real is held; the 25 kVA pump transformer, the 15 km feeder and the pump load are assumed (EXAMPLE). Real context: Telangana rooftop solar 695.9 MW as on 31.01.2026 (MNRE, REAL, a state total; it says nothing about farm feeders).
- Not held: Real transformer data (kVA, consumers, phase, 15-minute DTR or feeder load). Not public; the DTR list has to come from the department. Every network value here is assumed.